A building permit from a local municipality may need to be obtained.
Electric meter installation procedures.
Meter installation from pad mount transformer w vt pack 480v figure 15.
Connect the wires to the corresponding places on your new electrical meter by slipping them into the appropriate spot and screwing it down with the screwdriver.
Meter a device for measuring the electric power and energy supplied to a customer.
The customer shall install the meter socket or transformer cabinet so that it is plumb tight and level.
American electric power company meter and service guide 4 figure 14.
For electrical equipment mounted higher than 6 feet 6 inches this space shall extend to the top of the equipment.
We re dedicated to providing safe economical and reliable service.
The meters will be exchanged by meter reading routes.
Meter enclosure a wood or metal cabinet or metal socket installed indoors or outdoors in which the company s metering equipment is located.
Meter installation it is important that your new meter is installed in a safe maintained and easily accessible location.
Replacement of an existing meter on your home.
Installing or revising electric service there are five simple steps you must take to have electric service installed for the first time or revised at your residence.
Meter sockets a meter socket is the base portion of a socket type meter.
Apply for service step 3.
Plan your project step 2.
All mounting holes provided in the meter socket shall be used and no additional mounting holes shall be drilled.
480v delta or 277 480v wye 200 amp below service self contained metering with meter disconnect figure 16.
Any electrical installation involving the service entrance must comply with the local utility company s requirements.
All metallic meter boxes must be grounded.
Representatives 407 423 9018 to place an application for the meter installation and account application.
Coordinate with project lead step 4.
The line side wires should connect to the upper terminals on the new meter while the bottom terminals are for the load side wires.
The national electric safety code requires an unobstructed working space that extends from the floor or ground to a minimum height of 6 feet 6 inches.
When the inspection clearance and application have been received ouc will attempt to install a meter s within five 5 to seven 7 business days.
When the meter technician arrives they will knock on your door and present themselves.
Daily before starting work all meter technicians will be taking their temperature.
Your assigned xcel energy representative will work with you to find a meter location that will fit your project needs.
Three phase or ct service may require additional time for scheduling temporary.
Meter installation from pad mount transformer usi ng bushing type ct s figure 14b.